Auckland Transport's Practice Note 07 sets out seven approval processes a vehicle crossing can touch, each under its own statute (§1.4 and Attachment A).
| # | Approval | Under | Who approves it |
|---|
| 1 | Resource Consent (RC) | Resource Management Act | Auckland Council |
| 2 | Engineering Approval (EA), vehicle crossing portion | Resource Management Act | Assessed by Auckland Transport, approved by Auckland Council |
| 3 | Encroachment approval, for any structure or parking area in the road reserve | AT bylaw | Auckland Transport |
| 4 | Building Consent (BC), if required | Building Act | Auckland Council |
| 5 | Vehicle Crossing Permit | AT bylaw | Auckland Transport |
| 6 | Temporary Traffic Management Plan (TTMP), if required | Local Government Act | Auckland Transport (review) |
| 7 | Corridor Access Request (CAR) | AT bylaw | Auckland Transport |
Do not let the number put you off. Most straightforward residential jobs need three or four of these. The list is the full set of gates that can apply, not a checklist everyone completes.
The order Auckland Transport recommends you lodge them in
Auckland Transport publishes a preferred lodging order. It is recommended, not mandatory, so you are allowed to lodge out of order.
The reason to follow it anyway is money. Approvals earlier in the sequence can change the geometry of the crossing, and if you have already paid for drawings based on the old geometry, you redraw and re-lodge. The order exists to stop you buying the same design twice.
The hold point at the Vehicle Crossing Permit
The seven processes do not run in a single line. They split into three groups that progress in parallel:
- Resource Consent and Engineering Approval
- Encroachment Licence and Building Act matters
- Temporary Traffic Management Plan and Corridor Access Request
Those three streams converge at the Vehicle Crossing Permit application. That is the hold point. Whatever is outstanding in any of the three groups holds up the permit, and nothing starts on site until the permit is through. If a job is stalled and nobody can explain why, this is usually where it is sitting.
Which of the seven will my job actually need?
| What you are doing | Approvals typically in play | Where you start |
|---|
| New build on a site with no crossing | Building consent and Vehicle Crossing Permit; Engineering Approval and resource consent if the access misses Chapter E27 | Apply for the crossing with your building consent |
| Widening, moving, or adding a second crossing | Vehicle Crossing Permit; resource consent if it breaches E27; Encroachment if anything sits in the road reserve | Auckland Transport |
| Repairing the crossing at the footpath | Written AT approval; Corridor Access Request; TTMP if the footpath or traffic lane is affected | Auckland Transport |
| Shared crossing with a neighbour | Vehicle Crossing Permit plus written approval from each landowner; resource consent if separation or geometry misses E27 | Auckland Transport, with the written approvals already in hand |
Two more requirements catch people out. A Council-approved contractor must install the crossing, so you cannot do the road-reserve work yourself or use any contractor whose price you happen to like. And if the crossing adjoins a State Highway, you need NZ Transport Agency approval on top of everything above.
A note on figures you will see quoted. Several New Zealand driveway guides quote flat permit fees, fixed width limits such as "2.5 to 5.5 metres", and firm approval timeframes. None of those appear in Auckland Transport Practice Note 07 or in Chapter E27 of the Unitary Plan. Crossing width is not set as a fixed range at all: it is derived from your driveway width, as set out below. Check any number against its source before you budget around it.
Getting the sequence right is most of the job. For a free on-site quote anywhere in Auckland from a team that has taken driveways through the Auckland Transport process before, call 09 977 9966.